Home/Portfolio/Railway Track Bed with Structure along Simara-Bardibas Sector

Project Information

Railway Track Bed with Structure along Simara-Bardibas Sector

Completed Project

Category:Airport & Transport
Completed:February 15, 2018

Project Description

Ashish Nirman Sewa, as part of M/S Ashish-Lumbini-Contech Joint Venture, Bharatpur-10, Chitwan, successfully completed railway track bed and structure works along the Simara-Bardibas sector of the Mechi-Mahakali Electrified Railway Project.

The works covered chainage 100+000 to 102+300 and included gravel embankment, base course, concrete cross-drainage structures, and road under bridge works for the national railway corridor.

The project was completed on 15 February 2018 and certified by the Department of Railways, Rail, Metrorail and Monorail Development Project.

Key Works

Chainage: 100+000 to 102+300
Nature of Works: Gravel embankment, base course, cross-drainage structures and RUB works
Concrete Works (M30): 3,087.82 Cum
Concrete Works (M20): 276.94 Cum
Reinforcement Bar: 408.00 Ton
False Works: 1,082.39 Sqm
Bio-Engineering Works: 60,979.90 Sqm