Project Description
Ashish Nirman Sewa, as part of M/S Ashish-Sunil Samir JV, successfully completed the Construction of Runway and Retaining Structures Works of Gulmi (Resunga) Airport, Simichaur, Gulmi in Fiscal Year 2074/075 under the Aerodrome Engineering Department of the Civil Aviation Authority of Nepal.
The project involved construction of the runway and extensive retaining structures to enable airport operations in the hilly terrain of Gulmi district. The quality of the work and construction management undertaken by the contractor was highly appreciated by the employer.
The project was completed within the agreed timeline, delivering critical aviation infrastructure to improve connectivity for the Gulmi region.