Project Information

Khandbari Town Water Supply and Sanitation Project

Completed Project

Category:Water Supply & Sewerage
Completed:September 18, 2018

Project Description

M/S Sinotec-Ashish JV successfully completed the Khandbari Town Water Supply and Sanitation Project in Sankhuwasabha under the Second Small Town Water Supply and Sanitation Sector Project, funded by the Asian Development Bank.

The project was executed for the Government of Nepal, Department of Water Supply and Sewerage, Second Small Town Water Supply and Sanitation Sector Project under Contract No. SSTWSSSP/ICB-18/Khandbari_Sankhuwasabha.

The contract agreement date was 14 July 2013, with work starting on 1 August 2013. The certificate records an original contract amount of NRs. 348,376,524.79, revised contract amount of NRs. 434,587,715.92 with VAT excluding CPA, and total paid amount of NRs. 463,312,933.53 with VAT and CPA.

Key Works

Earthwork in Excavation: 92,189.31 M3
Backfilling in Excavation: 47,401.83 M3
M15 Concrete in Foundation and Floor: 503.49 M3
M20 RCC at Water Contact Wall and Base Slabs: 1,689.53 M3
Formwork: 7,131.74 M2
Random Rubble Stone Masonry in 1:4 C/S Mortar: 5,020.54 M3
Coarse Hammer Dry Stone Masonry: 1,156.08 M3
Tested Fe 415 Reinforcement Bar: 126,998.90 Kg
Gabion Work: 910.00 M3
Chlorination Injection Devices with FRP Tank and Dosing Pump: 2 Nos.
Sand Filling: 639.13 M3
Non-Crushed Gravel Filling: 548.32 M3
HDPE Pipeline: 68,349.12 Rm
GI Pipeline: 82,867.03 Rm
DI Pipeline: 15,650.66 Rm
Household Connections: 2,360 Nos.
LT Wire Installation: 1,350 Rm
Reservoir Tank 50 Cum: 3 Nos.
Reservoir Tank 75 Cum: 1 No.
Reservoir Tank 100 Cum: 2 Nos.
Roughening Filter: 2 Nos.
Slow Sand Filter Unit: 4 Nos.